Moorpark 25, Mirfield

About This Project

Electrical work includes:

     

  • New transformer and main switchboard
  • New distribution boards installation
  • Earthing and bonding
  • Containment installation
  • Supply and installation of lighting and emergency lighting to offices areas, process areas and workshops
  • Supply and installation of external lighting and lighting control systems
  • Small power installation to office areas, process areas and workshops
  • Mechanical plant power supplies
  • CCTV and security systems
  • Fire alarm installation works
  • Disabled systems
  • Data installations

 
Mechanical work includes:

     

  • Supply and installation of a new water supply, meter and pipework
  • Supply to the building plant room in accordance with Yorkshire Water guidelines
  • New gas housing, gas meter and pipework supply to the building plant room
  • LTHW heating system
  • Gas radiant heating to workshop and warehouse
  • Mechanical ventilation to WCs
  • Kitchen domestic including hot and cold water services
  • Above ground drainage
  • Gas and water mains services
  • Supply and installation of sanitary ware
  • HVAC within the office areas
VALUE

£379,000

SECTOR

Industrial warehousing

CONTRACT PERIOD

14 weeks

CATEGORY

Mechanical & electrical

  


Advise . Design . Supply . Install